Straw Bale Building and the Foundation

Straw bale building foundation in process with red tone to the concrete and plumbing showing.

Slab on grade foundation for straw bale building

There are many different options for foundations in straw bale building. Concrete stem walls and footings, piers, concrete slabs, rubble trench with concrete bond beam,  earth/sand bag, and rip-rap stacks are all possibilities. The biggest limitation may be the building department and what they will accept as meeting code.

In general, foundation systems contain one or more of the following:

  • footings

  • piers

  • stem walls

  • slabs

The two most common systems are slabs and stem walls with footings. Slabs can be very simple and are a great idea when excavation requirements are minimal. Stem walls are especially useful in areas with a deep frost line as more excavation will be required in those situations.

Building back with a stem wall may allow you to incorporate a basement in your plan.

Be sure to consider the geotechnical engineering requirements of your soil as well. Some jurisdictions actually require a geotechnical report these days, so check with your building department before making any decisions.

Slab on Grade Straw Bale Foundation

A floating slab can work in conjunction with basement walls; however, if you are not required to excavate below deep frost lines, a simple, insulated slab on grade will be much more practical. The slab provides for a floor system, foundation system, and heat sink all in one step. Create a heat sink by using materials with high thermal mass in an area that receives direct sunlight.

The sun heats the mass and then over time the stored heat is slowly released into the room. This is one of the major principles of passive solar design.

A concrete slab makes for an excellent heat sink. This is also true when using a radiant floor heating system. The large mass of the concrete slab provides for excellent thermal storage, lowering heating costs.

The Downside

As with any material, there are a number of downsides to using concrete. The production of the product itself is very damaging to the environment. Concrete, when used as a new product, has a huge embodied energy (EE) cost. The process of making Portland cement, an ingredient in concrete, creates a 100% embodied energy ratio. In other words, for every pound of Portland cement, one pound of carbon dioxide is produced. As much waste material as the product is created, yielding a 100% EE Ratio.

The addition of rip-rap, old pieces of cured concrete broken up into small slabs reduces the need for new materials. Minimal amounts of fly ash and incinerator ash can be added to the mix in place of Portland cement.

Some concrete companies do not offer this option, so check it out beforehand. One thing we know for sure is that the less concrete you use in your project, the more environmentally friendly it will be.

Mind the Details

Slabs are so popular because of the availability of the material and ease of construction (once you have figured it all out). With practice, you, too, can pour an attractive slab foundation. What’s more, there are loads of contractors available to choose from if you’d rather hire it out.

A basic slab consists of wide footings at the perimeter or wherever extra bearing is required, sub-slab gravel inside the footings, six mil plastic, insulation, a 2″ sand bed, and a rebar frame.

There are lots of site-specific details that should be considered when constructing your slab. Be sure to insulate well at the edges and underneath the slab to isolate the thermal mass to the inside of the structure. Not doing so will result in a very inefficient building due to heat loss through the concrete.

It is very important to get proper compaction of the sub-slab material in order to reduce cracking in the finished slab. Once the slab is formed, leveled, and squared, installing the above materials can be relatively quick and easy.

For example, a simple 200 square-foot slab can be prepared and poured by one person in about 2-3 days. Once poured, as with any concrete, you must wait a minimum of 45 days to allow for proper curing before you begin construction on the concrete.

Adding acid staining or broadcast color is another plus for concrete slabs. The timing of the application of these materials depends on the materials you choose. Broadcast colors are added during the steel toweling. Acid stain is added at the end of the job after the home is close to completion.

Basement Walls

In areas where deep excavation is essential to meet code, a basement may be the best option. Because you may be required to pour deep stem walls to get below the frost line, finishing these walls and creating a basement makes perfect sense. The added cost is minimal for the square footage you can realize.

Place the bale walls on a wood floor joist system spanning the basement stem walls. If the code in your area states that bearing is required for the entire width of the bales, you can minimize the use of concrete by adding a framed wall at the inner edge of the bales that bears on the basement floor slab rather than increasing the width of the concrete stem wall.

Insulating the framed walls and creating a physically and emotionally warmer room are great ideas, too. Running utility lines in this space simplifies their installation.

Waterproof The Basement Walls

Waterproofing the exterior of the basement walls is essential. There are many ways to accomplish this. The following system is economical and provides excellent waterproofing.

A waterproof membrane is placed against the foundation wall on the exterior of the building. On top of the membrane, use a sheet of drain material to channel water away from the foundation walls. Sheet drains are explicitly designed for this and consist of a formed polystyrene board covered on one side with filter fabric. The fabric is placed towards the soil and allows water to flow into the polystyrene board while minimizing the impact of the soil on the system. The sheet drain then wraps around a perforated pipe, which carries any water away from the foundation.

Conclusion

Whether you choose a basement wall or slab system, straw bales can work with your project. Check with your codes, decide on your design and plan for some hard labor.

No matter what system you use, concrete is physically challenging to work with. Set up your pours for mornings to allow yourself a full day to work with the concrete.

Pay attention to the weather, as rain will cause many problems when working with concrete, as will excessive heat. F

inally, make sure you’re ready for the concrete when the truck arrives. There is a time limit to how long concrete can spin before it starts to fire off. Don’t have a truck on site until you are sure that you are ready to go.

Above all, be open to the process of learning and try to have fun!

Looking for more step by step information? Check out our learning materials here

Next
Next

How to Choose a Contractor for your Strawbale Building